List of Bulk Consumers where we were associated for power supply
Work on turn-key basis |
|
Sl
No. |
Name of the Company |
Status of Company |
Nature of Work |
Load Demand |
Year of Work Execution |
1. |
Malda Metal Pvt. Ltd.
Amarpur,
Raghunath Ganj. Murshidabad. (Completed) |
Induction Furnace |
Supply & Erection of 33 kV overhead line & 33 kV. Sub-Stn. |
33 kV |
2003-04 |
2.
|
Sova Ispat Ltd.
Mejia, Bankura
(Completed) |
Sponge Iron |
Supply & Erection of 33kV overhead line 12 K.M.& Sub-Stn. |
33 kV |
2003-04 |
3.
|
National Highway Authority of India
New Delhi, India |
- |
National Highway
Expansion. |
- |
2003-04 |
1. |
Maa Amba Sponge Iron Pvt. Ltd.
Mejia, Bankura
(Completed) |
Sponge Iron |
Supply & Erection of 11K.V. overhead line 13 K.M.
& 11KV Indoor Sub-Stn. |
33 kV |
2004-05 |
2. |
Steel Crackers Pvt. Ltd.
Delhi Road, Hooghly.
(Completed) |
Induction Furnace & Rolling Mills |
Supply & Erection of 33kV overhead line 4.5 K.M.& 33kV Sub-Stn. |
33 kV |
2004-05 |
3. |
East India Flour Mills Pvt. Ltd.
(Steel Division)
Delhi Road Hooghly.
(Completed) |
Induction Furnace |
Supply & Erection of 33kV overhead line 3 K.M.& 33kV
Sub-Stn. |
33 kV |
2004-05 |
4. |
B.M.N. Alloy Steels Pvt. Ltd.
Delhi Road, Hooghly. (Completed) |
Induction Furnace |
Supply & Erection of 33kV overhead line 4.5 K.M.& 33kV. Sub-Stn. |
33 kV |
2004-05 |
|
|
List of Bulk Consumers where we were associated for power supply
Work on turn-key basis |
|
Sl
No. |
Name of the Company |
Status of Company |
Nature of Work |
Load Demand |
Year of Work Execution |
1. |
G.P.S. Steels Trade Linkers Pvt. Ltd.
Bishnupur, Bankura.
(Completed) |
Induction Furnace & Rolling Mills. |
Supply & Erection of 33 kV overhead line 3.8K.M. & 33kV Sub-Stn. |
33 kV |
2005-06 |
2.
|
Arjan Dass
Steel Casting Pvt. Ltd.
Delhi Road, Hooghly. (Completed) |
Induction Furnace |
Supply & Erection of 33 kV overhead line 0.7K.M.& 33kV Sub-Stn. |
33 kV |
2005-06 |
3. |
Shree Balaji Iron & Steel Co. Pvt. Ltd.
Delhi Road, Hooghly. (Completed) |
Induction Furnace |
Supply & Erection of 33kV overhead line & 33kV Sub-Stn. |
33 kV |
2005-06 |
4. |
Marotia Steel & Alloy Pvt. Ltd.
Delhi Road, Bhadreswar, Hooghly. (Completed) |
Forging Unit |
Supply & Erection of 11 kV overhead line & 11kV Indoor Sub-Stn. |
11 kV |
2005-06 |
5. |
Orion Metal Pvt. Ltd.
Delhi Road, Hooghly (Completed) |
Induction Furnace |
Supply & Erection of 11 kV overhead line 4.5K.M.& 11 kV Indoor Sub-Stn. |
11 kV |
2005-06 |
6. |
G.F.M. Agro Products Pvt. Ltd. Jalan Complex, Howrah.
(Completed) |
Flour Mills |
Supply & Erection of 11 kV overhead line & 11kV Indoor Sub-Stn. |
11 kV |
2005-06 |
7. |
J. P. Flour Mills Pvt. Ltd.
Bhadreswar, Hooghly.
(Completed) |
Flour Mills |
Supply & Erection of 11 kV overhead line & 11kV Indoor
Sub-Stn. |
11 kV |
2005-06 |
|
|
List of Bulk Consumers where we were associated for power supply
Work on turn-key basis |
|
Sl.
No. |
Name of the Company |
Status of Company |
Nature of Work |
Load Demand |
Year of Work Execution |
1. |
Balaji Metal & Sponge Pvt. Ltd.
Mejia, Bankura.
(Completed) |
Arc Furnace |
Supply & Erection of 11kV overhead line on Rail Pole & 11 kV Indoor Sub-Stn. |
33 kV |
2006-07 |
2.
|
Hooghly Alloy & Steels Co. Pvt. Ltd.
Delhi Road Hooghly.
(Completed) |
Induction Furnace |
Supply & Erection of 33 kV Sub-Stn. |
33 kV |
2006-07 |
3. |
Rajgaria Cera Tiles
Pvt. Ltd.
Delhi Road, Hooghly. (Not Completed due to Banking Finance of the Company) |
Tiles Factory |
Supply & Erection of 11kV overhead line & 11 kV Indoor Sub-Stn. |
11 kV |
2006-07 |
4. |
Tata Metalics Ltd.
Kharagpur,
West Midnapur.
(Completed) |
Pig Iron Factory |
Supply & Erection of 33kV overhead line on Rail Pole,
33 kV Spread Out Sub-Stn. & 33kV. Indoor Sub-Stn. |
33 kV |
2006-07 |
5. |
Druk Wang
Alloys Ltd.
Phuentsholing
Bhutan
(Completed) |
Ferro Alloy Plant |
Supply & Erection of 66 kV Sub Station on Structures. |
66 kV |
2006-07 |
|
|
List of Bulk Consumers where we were associated for power supply
Work on turn-key basis |
|
1. |
Tata Metaliks Kubota Pipes Ltd.
Kharagpur, Samraipur
Midnapur (W)
(Completed) |
DI Pipes Project |
Supply & Erection of Construction Power (11 kV) |
11 kV |
2007-08 |
2. |
Matchless Forging Pvt. Ltd.
Chakundi, Dankuni
Hooghly
(Completed) |
Forging Factory |
Supply & Erection of 11kV overhead line &
11 kV Indoor Sub-Stn. |
11 kV |
2007-08 |
4. |
Telco Construction Equipment Co. Ltd.
Tata Motors Premises,
Jamshedpur – 831 010
(Completed) |
Equipments Manufactur-ing Co. |
Supply & Erection of 11 kV overhead line &
11 kV Indoor Sub-Stn. |
11 kV |
2007-08
|
5. |
Tata Metaliks Kubota Pipes Ltd.
Kharagpur, Samraipur
Midnapur (W)
(Completed) |
DI Pipes Project |
Supply & Erection of 132kV Transmission Tower Line. |
132 kV |
2008-09 |
6. |
Reshmi Metaliks Ltd.
Kharagpur Samraipur
Midnapur (W)
(Completed) |
Coke Oven |
Supply & Erection of 33 kV overhead line on Rail Pole & 33 kV Sub-Stn. |
33 kV |
2008-09 |
|
|
Work under progress |
|
1. |
Brilliant Steel Product Pvt. Ltd.
Katwa Road, Burdwan. |
Rolling Mills |
Supply & Erection of 11 kV overhead line &
11 kV Indoor Sub-Stn. |
11 kV |
2008-09 |
2. |
Telco Construction Equipment Company Limited
Rupnaryanpur, Kharagpur,Midnapur (W) |
Equipment manufacturing Co. |
Supply and Erection of
33 kV Indoor Sub-Stn.and 33kV Transmission Line 17 KM. |
33 kV |
2008-09 |
3. |
Ganerwala Paper Mill.
Mogra, Hooghly. |
Cement manufacturing Co. |
Supply & Erection of 11 kV Indoor sub station. |
11 kV |
2008-09 |
4. |
Bharat Petrolium Ltd.
Polba, Hooghly |
Petrol Pump |
Supply & Erection of 11 kV Indoor sub station & Transmission Line. |
11 kV |
2008-09 |
5. |
Rattan Loha Udyog Pvt. Ltd
Delhi Road, Polba, Hooghly |
Induction Furnace |
Supply & Erection of 33 kV Outdoor sub-stn. & 33 kV Transmission Line. |
33 kV |
2009-10 |
6. |
Marotia Steel & Alloys Pvt. Ltd.
Delhi Road,Bhadreswar, Hooghly |
Forging & Induction Furnace |
33 kV Transmission Line & Outdoor Sub-Stn. |
33 kV |
2009-10 |
|
|
|
|
|
|