Sl.
No. |
Name of the Company |
Status of Company |
Nature of Work |
Load Demand |
Year of Work Execution |
1. |
Balaji Metal & Sponge Pvt. Ltd.
Mejia, Bankura.
(Completed) |
Arc Furnace |
Supply & Erection of 11kV overhead line on Rail Pole & 11 kV Indoor Sub-Stn. |
33 kV |
2006-07 |
2.
|
Hooghly Alloy & Steels Co. Pvt. Ltd.
Delhi Road Hooghly.
(Completed) |
Induction Furnace |
Supply & Erection of 33 kV Sub-Stn. |
33 kV |
2006-07 |
3. |
Rajgaria Cera Tiles
Pvt. Ltd.
Delhi Road, Hooghly. (Not Completed due to Banking Finance of the Company) |
Tiles Factory |
Supply & Erection of 11kV overhead line & 11 kV Indoor Sub-Stn. |
11 kV |
2006-07 |
4. |
Tata Metalics Ltd.
Kharagpur,
West Midnapur.
(Completed) |
Pig Iron Factory |
Supply & Erection of 33kV overhead line on Rail Pole,
33 kV Spread Out Sub-Stn. & 33kV. Indoor Sub-Stn. |
33 kV |
2006-07 |
5. |
Druk Wang
Alloys Ltd.
Phuentsholing
Bhutan
(Completed) |
Ferro Alloy Plant |
Supply & Erection of 66 kV Sub Station on Structures. |
66 kV |
2006-07 |